Significant Traffic Impacts & Construction

W. A St. at Gateway
 August 15, 2023 - May 31, 2024
 7:00 am – 4:00 pm
Impacted areas: West A St. from Whispering Way to the I-80 overpass. Temporary single-lane closures with alternating flagger-controlled traffic. For a full map click here.

W. A St. at Pitt School Rd
 February 12, 2024 – May 31, 2024
 7:30 am – 4:30 pm

Impacted areas: Intersection of West A St. and Pitt School Rd. for Homestead utility trenching. Periodic single-lane closures on Pitt School Rd. For detour map click here.

Pitt School Road south of West A St. 
April 24, 2024 – May 31, 2024 
7:00 am – 5:00 pm 
Impacted areas: Pitt School Road from Homestead Way south to city limits. Heavy truck traffic in the area due to Homestead development soils off-haul. 

W. B St. from N. Washington to N. Adams
April 22, 2024 – May 31, 2024
7:00 am – 5:00 pm
Impacted areas: W. B St. between N. Washington and N. Lincoln for Cal Water main replacement project. Road closed to street parking and through traffic. Access to local residents and emergency services maintained at all times. For affected area map click here.